dc.identifier.citationNieto-Morote, A., Ruz-Vila, F. Last planner control system applied to a chemical plant construction. Journal of Construction Engineering and Management, Vol. 138, No. 2, February 2012, pp. 287-293es_ES
dc.identifier.issn1943-7862
dc.description.abstractThe main difference between the Last Planner production control system developed by Ballard and classical control systems is the way in which projects are controlled and planned. The Last Planner system focuses on controlling production units, workflows and the quality of the performed work. It also permits the identification of the causes for the non-completion of planned work and decision making in accordance with the project requirements so that actions are timely and productivity is increased. The objective of this paper is to present the results obtained from implementing the Last Planner system in the construction department of a chemical company. In this department, an information flow problem was detected among its members, in which supervisors lacked knowledge about the work to be performed until the project had been perfectly designed. This problem often led to meant long delays in the projects. The results from Last Planner system implementation show that identifying the constraints of the planned work leads to an improvement in the percentage and quality of completed activitieses_ES
dc.formatapplication/pdfes_ES
dc.language.isoenges_ES
dc.publisherAmerican Society of Civil Engineers, Journal of Construction Engineering and Managementes_ES
dc.rightsAtribución-NoComercial-SinDerivadas 3.0 España*
dc.rights.urihttp://creativecommons.org/licenses/by-nc-nd/3.0/es/*
dc.titleLast planner control system applied to a chemical plant constructiones_ES
dc.typeinfo:eu-repo/semantics/articlees_ES
dc.subject.otherProyectos de Ingenieríaes_ES
dc.subjectProject managementes_ES
dc.subjectLast planneres_ES
dc.subjectProject performancees_ES
dc.identifier.urihttp://hdl.handle.net/10317/4037
dc.peerreviewes_ES
dc.contributor.investgroupIngeniería Eléctrica y Energías Renovables (IEER)es_ES
dc.identifier.doi10.1061/(ASCE)CO.1943-7862.0000415
dc.rights.accessRightsinfo:eu-repo/semantics/openAccesses_ES
dc.type.versioninfo:eu-repo/semantics/acceptedVersiones_ES


Ficheros en el ítem

untranslated

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Atribución-NoComercial-SinDerivadas 3.0 España
Excepto si se señala otra cosa, la licencia del ítem se describe como Atribución-NoComercial-SinDerivadas 3.0 España