Last planner control system applied to a chemical plant construction
View/ Open
Share
Statistics
View Usage StatisticsMetadata
Show full item recordResearch Group
Ingeniería Eléctrica y Energías Renovables (IEER)Knowledge Area
Proyectos de IngenieríaPublication date
2012-02Publisher
American Society of Civil Engineers, Journal of Construction Engineering and ManagementBibliographic Citation
Nieto-Morote, A., Ruz-Vila, F. Last planner control system applied to a chemical plant construction. Journal of Construction Engineering and Management, Vol. 138, No. 2, February 2012, pp. 287-293Peer review
SíKeywords
Project managementLast planner
Project performance
Abstract
The main difference between the Last Planner production control system developed by Ballard and classical control systems is the way in which projects are controlled and planned. The Last Planner system focuses on controlling production units, workflows and the quality of the performed work. It also permits the identification of the causes for the non-completion of planned work and decision making in accordance with the project requirements so that actions are timely and productivity is increased.
The objective of this paper is to present the results obtained from implementing the Last Planner system in the construction department of a chemical company. In this department, an information flow problem was detected among its members, in which supervisors lacked knowledge about the work to be performed until the project had been perfectly designed. This problem often led to meant long delays in the projects.
The results from Last Planner system implementation show that identifying the ...